Key takeaways
- Budget vs actual compares what your business planned to earn and spend in a period with what it actually earned and spent. The difference is the budget variance.
- Budget variance = actual − budget. Variance % = (actual − budget) ÷ budget × 100. Percent of budget used = actual ÷ budget × 100.
- Over budget is unfavorable on a cost line and favorable on a revenue line, so label every variance favorable or unfavorable instead of relying on the sign.
- A useful budget vs actual report explains only the variances above a set threshold, says whether each one is timing or permanent, and shows what it means for the forecast.
Budget vs actual is a comparison of what your business planned to earn and spend in a period with what it actually earned and spent. The difference between the two is the budget variance, shown in dollars and as a percentage of the budget. Finance teams review it every month, after the close, to catch overspending early, hold budget owners accountable, and keep the forecast accurate.
Budget vs actual formulas
- Budget variance= Actual − Budget
- Variance %= (Actual − Budget) ÷ Budget × 100
- Percent of budget used= Actual ÷ Budget × 100
Example
Marketing budgeted $50,000 for October and spent $56,000. The variance is $6,000 over budget, the variance % is 12%, and the team used 112% of its budget. On a cost line, over budget is unfavorable.
- Sign conventionActual minus budget is positive when actual comes in above plan. On revenue and profit lines, a positive variance is favorable. On cost and expense lines, a positive variance is unfavorable.
What is budget vs actual?
Budget vs actual is the monthly check of your financial results against the plan leadership approved, run once the month-end close is complete so the actuals are final.
- BudgetThe approved plan for revenue and expenses, usually set once a year and split by month
- ActualsThe recorded results for the period, taken from your closed books
- Budget varianceThe difference between actual and budget for each line, in dollars and as a percentage
You'll also see the comparison called budget to actual, budget vs actuals, or actual vs budget. They all describe the same analysis. For how it fits into the wider planning cycle, see what FP&A is.
Budget vs actual variance formula
The budget vs actual variance formula is actual minus budget in dollars, and the variance percentage formula is (actual − budget) ÷ budget × 100. Each formula answers a different question:
| Measure | Formula | What it tells you | Example: March sales and marketing, budget $300,000, actual $345,000 |
|---|---|---|---|
| Budget variance ($) | Actual − Budget | How far off plan the line is, in dollars | $345,000 − $300,000 = $45,000 |
| Variance % | (Actual − Budget) ÷ Budget × 100 | How large the miss is relative to the plan | $45,000 ÷ $300,000 × 100 = 15.0% |
| Variance % (same result, other form) | (Actual ÷ Budget − 1) × 100 | The same percentage, calculated in one step | (1.15 − 1) × 100 = 15.0% |
| Percent of budget used | Actual ÷ Budget × 100 | How much of the budget has been spent | $345,000 ÷ $300,000 × 100 = 115% |
| Percent of budget remaining | (Budget − Actual) ÷ Budget × 100 | How much budget is left; negative means overspent | ($300,000 − $345,000) ÷ $300,000 × 100 = −15% |
Because sales and marketing is a cost line and actual is higher than budget, the $45,000 variance is unfavorable.
How do you calculate actual variance?
To calculate actual variance, subtract the budgeted amount from the actual amount for the same line and period: actual variance = actual − budget. A positive result means actual came in above plan, and a negative result means it came in below.
Example
March revenue was budgeted at $1,200,000 and came in at $1,150,000. The actual variance is $1,150,000 − $1,200,000 = −$50,000, or −4.2%. Revenue below plan is unfavorable.
How do you calculate percentage of budget vs actual?
To calculate the percentage of budget vs actual, divide actual by budget and multiply by 100. Subtract 100 from the result to get the variance percentage.
Example
$56,000 ÷ $50,000 × 100 = 112%, so the marketing team used 112% of its budget and ran 12% over.
Budget owners use percent of budget used to track spend during the month. The month-end report uses the variance percentage.
Do you subtract budget from actual or actual from budget?
The common convention is actual minus budget, which is what the formulas above use, with each variance then labeled favorable or unfavorable. Some teams flip the sign for expense lines so that a positive number always means favorable. Either approach works, as long as the report states which one it uses and applies it to every line.
Two cases need care:
- Zero budgetThe variance percentage can't be calculated when the budget is $0. Show the dollar variance and mark the percentage "n/m" (not meaningful).
- Negative budgetDivide by the absolute value of the budget so the sign stays correct.
Example
A business unit budgeted an operating loss of −$100,000 and lost $80,000. The variance is −$80,000 − (−$100,000) = $20,000. Dividing by $100,000 gives +20%, which is favorable. Dividing by −$100,000 would show −20% and make the result look worse than plan.
How do you calculate budget variance in Excel?
In Excel, put the budget in column B and the actual in column C, then use these formulas in row 2 and fill them down:
| Column | Excel formula | Notes |
|---|---|---|
| Variance ($) | =C2-B2 | Actual minus budget |
| Variance (%) | =IF(B2=0,"n/m",(C2-B2)/ABS(B2)) | Format the cell as a percentage. ABS keeps the sign correct for negative budgets |
| Percent of budget used | =IF(B2=0,"n/m",C2/B2) | Format the cell as a percentage |
| F/U for a cost line | =IF(C2>B2,"U","F") | Spending above budget is unfavorable |
| F/U for a revenue line | =IF(C2>=B2,"F","U") | Revenue above budget is favorable |
Favorable vs unfavorable variances
A favorable variance improves profit compared with the plan, and an unfavorable variance reduces it, so the same sign means good news on revenue and bad news on costs:
| Line type | Actual above budget | Actual below budget |
|---|---|---|
| Revenue and other income | Favorable | Unfavorable |
| Cost of goods sold and operating expenses | Unfavorable | Favorable |
| Profit lines, such as gross profit and operating income | Favorable | Unfavorable |
A favorable variance isn't always good news. Spending less than budget on hiring can mean open roles that will slow the business later, so every significant variance still needs an explanation.
Marketing budget vs actual example
A marketing budget vs actual report compares each marketing spend category with its budget for the month, so you can see which lines drive the total variance.
Example
The October marketing budget from the formulas above breaks down like this:
| Line | Budget | Actual | Variance ($) | Variance (%) | % of budget used | F/U |
|---|---|---|---|---|---|---|
| Paid ads | $25,000 | $27,500 | $2,500 | 10.0% | 110.0% | U |
| Events | $12,000 | $18,000 | $6,000 | 50.0% | 150.0% | U |
| Software | $5,000 | $4,600 | −$400 | −8.0% | 92.0% | F |
| Contractors | $8,000 | $5,900 | −$2,100 | −26.3% | 73.8% | F |
| Total marketing | $50,000 | $56,000 | $6,000 | 12.0% | 112.0% | U |
The total is 12% over budget, but the line detail tells a sharper story. Events alone ran $6,000 over, which equals the entire overspend. Paid ads added $2,500, and the $2,500 underspend on software and contractors offset it. The contractor underspend may be timing, such as a project that slipped to November, so check before treating it as savings.
Marketing actuals are often incomplete at month-end because event and agency invoices arrive late. Book accrued expenses for work delivered but not yet billed. Otherwise a line can look under budget in October and over budget in November when the invoice lands.
How do you compare actual costs vs budget in a management report?
To compare actual costs vs budget in a management report, list each line with its budget, actual, variance in dollars and percent, a favorable or unfavorable label, and a one-line comment on the cause. Set a threshold first, so you only write comments for the variances that matter.
Example
A software company comments on any variance above $25,000 or 10%. Its March report looks like this:
| Line | Budget | Actual | Variance ($) | Variance (%) | F/U |
|---|---|---|---|---|---|
| Revenue | $1,200,000 | $1,150,000 | −$50,000 | −4.2% | U |
| Cost of goods sold | $360,000 | $333,500 | −$26,500 | −7.4% | F |
| Gross profit | $840,000 | $816,500 | −$23,500 | −2.8% | U |
| Sales and marketing | $300,000 | $345,000 | $45,000 | 15.0% | U |
| Research and development | $250,000 | $238,000 | −$12,000 | −4.8% | F |
| General and administrative | $150,000 | $152,000 | $2,000 | 1.3% | U |
| Operating income | $140,000 | $81,500 | −$58,500 | −41.8% | U |
| Line | Comment |
|---|---|
| Revenue | Two enterprise deals worth $60,000 closed on April 3 instead of in March. Expansion revenue added $10,000. Timing, so the full-year forecast is unchanged. |
| Cost of goods sold | A hosting discount that started in March saved $15,000, and lower usage saved $11,500. The discount is permanent and lowers full-year cost of goods sold by $150,000. |
| Gross profit | Explained by revenue and cost of goods sold above. |
| Sales and marketing | $35,000 is a trade show moved from May to March, which is timing. $10,000 is a new agency retainer that runs through December and is permanent. |
| Research and development | Below threshold. |
| General and administrative | Below threshold. |
| Operating income | $95,000 is timing from the revenue slip and the trade show, which reverses by May. Excluding timing, operating income is $36,500 ahead of budget. |
The threshold flags revenue, cost of goods sold, and sales and marketing, along with operating income, which those lines explain. Research and development and general and administrative stay below it, so they need no explanation this month.
What should a variance comment say?
A good variance comment gives the cause, the dollar amount of each driver, whether the variance is timing or permanent, and what it means for the forecast. Check that the drivers add up to the full variance: −$60,000 + $10,000 = −$50,000 for revenue, $15,000 + $11,500 = $26,500 for cost of goods sold, and $35,000 + $10,000 = $45,000 for sales and marketing. Commentary that doesn't reconcile to the variance usually means part of the cause is still missing.
Avoid comments that restate the number, such as "Revenue $50,000 under budget" or "Marketing overspent." They tell leadership nothing the columns don't already show.
What other columns do management reports add?
Many management packs add year-to-date and full-year columns, so readers see the trend as well as the month:
- Year-to-date budget and actualShows whether a monthly miss is a one-off or part of a pattern
- Prior year, same monthShows growth and separates seasonality from a real miss
- Full-year budget and latest forecastShows where the year will land if current trends continue
How to do a budget vs actual analysis
A consistent monthly routine helps you finish the analysis quickly and keeps the commentary comparable from month to month:
- Start from closed booksRun the analysis after the month-end close, so actuals include accruals and adjustments.
- Map actuals to budget linesMake sure each account rolls up to the same lines the budget uses.
- Calculate the variancesWork out the dollar and percentage variance for every line, and label each one favorable or unfavorable.
- Apply your thresholdExplain only the lines above it, such as $25,000 or 10% for a mid-sized company. There's no universal standard, so size the threshold to your company.
- Find the driverTrace each flagged variance to the transactions behind it and to one of the causes in the next section.
- Write the commentaryState the cause, the amount, and whether the variance will continue.
- Update the forecastCarry permanent variances into the next reforecast.
For the full month-end sequence that produces the actuals, see the month-end close process.
What causes budget variances?
Most budget variances come from one of five causes: timing, volume or mix, price or rate, a one-off event, or an error.
- TimingRevenue or spending landed in a different month than planned, and it will reverse
- Volume or mixYou sold, bought, or hired more or fewer units than planned, or sold a different mix of products
- Price or ratePrices, wages, or supplier costs differ from the plan
- One-offAn event the budget didn't include, such as a legal settlement
- ErrorA cost coded to the wrong account or posted to the wrong month, which should be corrected
The cause decides what happens next. Timing reverses on its own, errors get corrected in the books, one-offs affect only the period they hit, and volume and price changes usually carry into the reforecast.
Why compare budget vs actual?
The purpose of comparing budget vs actual is to find out early where the business is departing from its plan, and why. The main benefits are:
- Early warningA cost line running 15% over budget in March is easier to correct than the same overspend found in November
- AccountabilityEach budget owner explains the variances in their area, so spending decisions have a named owner
- Better forecastsVariances that will continue feed straight into the next reforecast, so the outlook reflects what's actually happening
- Clear decisionsLeadership sees which variances are timing and which are permanent, so it can decide what to act on
The work takes significant time. In Ledge's April 2025 survey of 100 finance professionals, variance and budget vs actual analysis ranked fourth among the five most time-consuming month-end close activities. FP&A Trends' 2025 survey, published in July 2025, found that 46% of FP&A time is still spent on data collection and validation rather than analysis.
Budget vs actual vs forecast
Budget vs actual measures performance against the fixed annual plan, while actual vs forecast measures it against your latest expectation, and leadership usually wants both:
| Comparison | Question it answers | When it changes |
|---|---|---|
| Actual vs budget | How are you performing against the plan leadership approved? | The budget stays fixed for the year |
| Actual vs forecast | How accurate is your latest expectation? | The forecast is updated monthly or quarterly |
| Forecast vs budget | Where will the full year land compared with the plan? | Each time you reforecast |
| Actual vs prior period | What changed since last month or last year? | Every month |
The budget gives you a stable baseline, while the forecast shows where the year is heading. Comparing actuals with the prior period instead of the plan is flux analysis. Accounting teams run it during the close to catch errors in the books, and FP&A runs budget variance analysis after the close to measure performance against the plan.
How often should you review budget vs actual?
Review budget vs actual every month, a few days after the close, and reforecast at least quarterly. The work involves several roles:
| Role | What they do |
|---|---|
| Controller | Confirms the actuals are final after the close |
| FP&A analyst | Builds the report, applies the threshold, and drafts questions |
| Budget owners | Explain the variances in their departments |
| FP&A lead | Reviews the commentary and updates the forecast |
| CFO | Reviews the report with leadership and decides what to act on |
The finished report usually goes into the monthly management pack.
How to create a budget vs actual report in your accounting system
QuickBooks Online, NetSuite, and Xero each include a standard budget vs actual report once you load the budget:
- QuickBooks OnlineThe Budget vs. Actuals report compares each account with its budget by month
- NetSuiteThe Budget vs. Actual report compares results with a budget by period and segment
- XeroThe Budget Variance report shows budget, actual, and variance for each account
These reports calculate the variances, but they don't explain them. To group accounts into budget lines, apply a threshold, and add commentary, export the numbers to Excel or an FP&A tool. The report example above works as a budget vs actual template in Excel: six columns for line, budget, actual, variance in dollars, variance in percent, and favorable or unfavorable, plus a seventh for commentary.
Software can also take on the investigation itself, such as tracing a variance to the transactions behind it and drafting the explanation for review. If you want to see how our agents prepare the monthly management report and its commentary for your review, explore the FP&A Agent.