What is retainage? Definition, example, and journal entry

Accounts receivable, billing and collections

Definition

Retainage (holdback) is the portion of a contract payment, often 5 to 10 percent, withheld by the customer until the project is satisfactorily completed. The contractor records it as retainage receivable when its right to payment is unconditional, or as a contract asset when payment depends on completion, acceptance, or lien waivers; either way it's usually a current asset, and the customer records retainage payable. It's also called retention.

Often withheld
5 to 10 percent
Contractor records
Retainage receivable or contract asset
Customer records
Retainage payable
Also called
Holdback or retention

What is retainage in construction?

In construction, retainage is the share of each progress payment the owner holds back until the work is done, so the contractor finishes the punch list and fixes defects.

The owner holds it from the general contractor, who often holds retainage from subcontractors too. Retention (UK) and holdback (Canada) mean the same thing. It isn't a fee; it's earned money paid later.

How to calculate retainage

Retainage is the amount billed for the period times the retainage rate; the cash due now is the billing minus that retainage.

Retainage = Amount billed this period × Retainage rate

Cash due now = Amount billed this period − Retainage

At 5%, a $100,000 bill pays $95,000 now and $5,000 later; at 10%, $90,000 and $10,000.

Is retainage an asset or a liability?

Retainage is an asset for the contractor (retainage receivable, or a contract asset while payment is conditional) and a liability for the customer (retainage payable). Contractors usually show it as current under their operating cycle, even if release is over a year away.

$668.9Mof retention receivable in current assets

Tutor Perini's Form 10-K for the year ended December 31, 2025, signed February 26, 2026, reports $668.9 million of retention receivable in current assets, balances it says could be outstanding "for several months or years."

Under ASC 606, it's generally a receivable if only time stands before payment, or a contract asset if payment depends on completion or acceptance. Practice varies: Tutor Perini treats its retention as an unconditional right to cash.

Retainage receivable vs accounts receivable

Retainage receivable is earned but not yet due; accounts receivable is due now on normal terms. Keep retainage separate so the AR aging shows only collectible balances.

Retainage example and journal entries

Ridgeline Builders, a general contractor, has a $400,000 contract with 10% retainage. Revenue is recognized over time (cost-to-cost) and equals each month's billing. Release depends on final lien waivers, so Ridgeline's right to the retainage isn't unconditional, and it books the holdback as a contract asset until it can invoice it. All amounts are illustrative.

DateAccountDebitCredit
Mar 31, 2026Accounts receivable135,000
Contract asset, retainage15,000
Contract revenue150,000
Apr 30, 2026Accounts receivable225,000
Contract asset, retainage25,000
Contract revenue250,000
May 29, 2026Cash360,000
Accounts receivable360,000
Jun 12, 2026Accounts receivable40,000
Contract asset, retainage40,000
Jun 30, 2026Cash40,000
Accounts receivable40,000
Total840,000840,000

The owner pays both bills, net of retainage, on May 29. On June 12, after final lien waivers, Ridgeline invoices the retainage, moving $40,000 into accounts receivable, and is paid June 30.

Contract asset (retainage) roll-forward, March 1 to May 31, 2026Amount
Beginning balance, March 1$0
Add: withheld on March 31 bill (10% of $150,000)15,000
Add: withheld on April 30 bill (10% of $250,000)25,000
Less: released0
Ending balance, May 31$40,000
Retainage schedule by project, May 31$40,000
Difference$0

In QuickBooks Online, track retainage in its own account with the Retainage detail type.

When is retainage recognized as revenue?

Retainage is revenue when you perform the work, not when it's released or paid. It usually isn't a significant financing component under ASC 606, because it protects against unfinished work rather than financing it.

What is retainage payable?

Retainage payable is the customer's side: the held-back amount it owes, a current liability until release.

DateAccountDebitCredit
Mar 31, 2026Construction in progress150,000
Accounts payable135,000
Retainage payable15,000
Total150,000150,000

On release, the owner debits retainage payable and credits accounts payable or cash. A general contractor carries both sides, often paying subcontractors after the owner releases, which squeezes their cash flow.

When is retainage paid or released?

Retainage is usually released at substantial or final completion, whichever the contract names, after the punch list and final lien waivers, and billed on a separate invoice.

Many states cap rates and set release deadlines, especially on public projects. A retainage bond lets a surety guarantee the work so the cash is released early.

What is retainage confused with?

Retainage is confused with receivables, contract assets, and the contract terms below; only retainage is earned money held back until completion.

TermWhat it isHow it differs from retainage
Accounts receivable (AR)Money customers owe a company for goods or services delivered on credit, recorded as a current asset until collectedDue now on normal terms; retainage isn't due until release conditions are met
Contract asset and contract liabilityA contract asset is a right to payment that depends on something other than time (an unconditional right is a receivable), while a contract liability is payment received or due before deliveryRetainage conditioned on completion or acceptance can be a contract asset
Retainer or depositAn upfront payment a customer makes before work starts, held as a liability until earnedPaid early by the customer; retainage is paid late
Performance bondA surety's guarantee that the contractor will finish the work, or the surety will pay to finish itA third-party guarantee, not cash withheld
Liquidated damagesA pre-agreed amount the contractor owes for delay or another breachKept by the customer as damages; retainage is paid once release conditions are met
ContingencyA budget allowance for unforeseen costsA reserve in the budget, not part of a payment

Retainage at month end

At month end, tie retainage to the project schedule and keep it out of collectible AR during the month-end close.

  1. Tie-out: Match the retainage schedule by project to the general ledger
  2. Releases: Reclassify released retainage to accounts receivable
  3. Credit losses: Include retainage in your allowance review
  4. Payables: Check subcontractor retainage payable against owner releases

For cash flow forecasts, schedule each expected release date. Our Close Agent prepares the AR subledger tie-out as a close task, and nothing posts until a named approver signs off.

Common retainage mistakes

The most common retainage mistakes are tying revenue to billing and misclassifying the balance.

  • Crediting revenue for whatever you bill: Revenue follows work performed; billings ahead of it are a contract liability
  • Calling it noncurrent: Contractors usually classify it as current under the operating cycle
  • Showing it as past due: It isn't overdue until release conditions are met and it's billed
  • Assuming one release rule: The contract and state law decide between substantial and final completion